4th November 2008, 02:49 PM
Hi everyone, this is my first time on this forum and i look forwards to making a contribution.
i have a question relating to an existing factory distribution setup, a 50mm 3Ph+N ring has been installed feeding 2x100A 3ph 32way and 1x200A 3ph 16 way distribution boards, i know this circuit is grossly overloaded to begin with (as it pops its 200A fuse everyother day) but i have no idea if such a high powered ring is permissable as far as the regs go, it's obviously bad practise but whats your opinions
thanks
i have a question relating to an existing factory distribution setup, a 50mm 3Ph+N ring has been installed feeding 2x100A 3ph 32way and 1x200A 3ph 16 way distribution boards, i know this circuit is grossly overloaded to begin with (as it pops its 200A fuse everyother day) but i have no idea if such a high powered ring is permissable as far as the regs go, it's obviously bad practise but whats your opinions
thanks